Ongoing & Future Projects

 

Ongoing Projects

 

 

 

Future Projects

 

 

 

Mahagenco is implementing capacity additions programmes of about 9320 MW. Project execution works of 3230 MW are in full swing and 6090 MW projects are in advanced stages of planning.

Mahagenco is aware of next green power scenario of power generation from non conventional energy resources and have clear vision for Green Power for the consumers of Maharashtra. Accordingly to fulfill Renewable Power obligation of distribution companies in Maharashtra, Mahagenco has commisioned 130 MWp Solar Power Projects till date. Mahagenco aspires to increase its solar portfolio from current 130 MWp to 450 MWp by end of the year 2015-16.

Mahagenco is implementing R&M work of 210 MW unit at Koradi. Feasibility study for implementation of R&M work at Chandrapur, Koradi, Bhusawal, Parli & Nasik is also being carried out.

 

       MAHAGENCO'S CAPACITY ADDITION PROGRAMME

      A.  COMPLETED PROJECTS (2500 MW): Capacity Added in 11th Plan (2007-2012)

Name of the Project Unit No. Unit Capacity (MW) Zero Date Date of Full Load/COD Cap. Addition During Year Year of Commisioning
Parli TPS 6 250 14.01.2004 19.05.2005 / 01.11.2007 500 MW 2007-2008
Paras TPS 3 250 25.05.2004 10.03.2008 / 31.03.2008
Parli TPS 7 250 31.08.2006 10.02.2010 / 31.07.2010 500 MW 2009-2010
Paras TPS 4 250 23.01.2007 27.03.2010 / 31.08.2010
Khaperkheda TPS Expansion Project 5 500 01.11.2007 05.08.2011 / 16.04.2012 500 MW 2011-2012  
Bhusawal TPS Expansion Project 4 500 23.01.2007 07.03.2012 / 16.11.2012 1000 MW
 
Bhusawal TPS Expansion Project  5 500 23.01.2007 30.03.2012 / 03.01.2014
 Total   2500        

 

   B.   ONGOING PROJECTS (3230 MW): Capacity Addition in 12th Plan (2012-2017)

 

Name of the Project Unit No. Unit Capacity (MW) Zero Date Commisioning Date Present Status Cap. Addition During Year Year of Commisioning
Koradi TPS 8 660 23.09.2009 Expected by March 2015 Boiler Light-up: 11.09.2014 1160 MW 2014-2015
Chandrapur TPS 8 500 09.02.2009 Expected by March 2015 Oil Flushing Completed- 09.08.2014
Parli TPS 8 250 20.01.2009 Expected by April 2015 Hydraulic Test (D)- 25.12.2012 2070 MW    2015.2016   
Chandrapur TPS 9 500 09.02.2009 Expected by June 2015 Condensor & TG Erection Started: 14.11.2013
Koradi TPS 9 660 23.09.2009 Expected by August 2015 TG Box-up: 28.07.2014 
Koradi TPS 10 660 23.09.2009 Expected by December 2015 Hydraulic Test- 05.07.2014
 Total   3230          

 

C.   FUTURE PROJECTS: Capacity Addition in 13th Plan (2017-2022)

 

Name of Project Capacity in MW Commisioning Year Present Status
Bhusawal Unit 6 1 x 660 2018-2019 Bid submitted againt tender on EPC carried out on 13.01.2014. After scrutiny of Technical and Commercial bids, order shall be placed on the successful bidder.
Paras Unit 5 1 x 250 2018-2019

Land acquired - 110.92 H

MOEF TOR Received - 07.09.2012

Nasik Unit 6 (Replacement) 1 x 660 2019-2020

Engineering & Tender preparation in process. The Public Hearing is conducted successfully on 07.05.2013.

Correspondence for getting final EC is in process.   

Dondaicha Project  5 x 660

2020-2021

to

2022-2023

Land acquisition is in progress (515.86 H land acquired).

Correspondence for getting final EC is in process.

 Uran GTPS

Block-I: 406

Block-II: 814

2019-2020* Tender for Lumpsum turnkey contract for installation of 1220 MW advance class gas turbine based CCPP cancelled in view of CEA's circular dt. 19.03.2012 in respect of non-availability of domestic gas for the gas based projects and advised not to plan gas based project till 2015-2016.

 Subject to availabilty of gas.

 

 D. SOLAR PROJECTS:

To fulfill Renewable Power Obligation of Mahadiscom, Mahagenco has planned to setup the Solar Power Projects in Mahrashtra.

 

FINANCIAL YEAR

Target MW Capacity
as per SOLAR RPO

Fulfilment by
Mahagenco (MWp)

Details of Solar Project
COMPLETED PROJECTS:
2010-2011 118  (0.25%) 1

1 MWp (April 2010)
CSTPS, Chandrapur

130 MWp
 2011-2012  129  (0.25%) 5

2 MWp (Oct 2011) &
2MWp (Feb 2012)
 CSTPS, Chandrapur

2012-2013 142  (0.25%) 130

125 MWp (March 2013)
Sakhari, Dist. Dhule

ONGOING PROJECTS:    
 2014-2015 344  (0.5%) 180

36+14 MWp (March 2015)
Shirsuphal Baramati through PPP

50 MWp
FUTURE PROJECTS:     
 2015-2016 379  (0.5%) 450

50 MWp - Kaudgaon, (Phase-I)
25 MWp - Sakhari, Dhule
(PPP bidding for above Projects are in progress)
50 MWp - Kaudgaon, (Phase-II)
50 MWp - Gangakhed
80 MWp - Mangladevi, Yawatmal
15 MWp - Aanterveli, Parbhani

270 MWp

 

E.  RENOVATION & MODERNIZATION (R&M) OF OLD UNITS TO IMPROVEMENT PERFORMANCE:

 Station

Project Title

 Project Start Date

Project Completion Date Cost of Project (in Crores)
Koradi India: Coal Fired Generation Rehabilitation on Project Koradi Unit-6 (210 MW) March-2014 Sept-2016 486